Ä¢¹½TVÏÂÔØ

Return
Location:
Juliette, GA
Completed:
2020

Units 1-4 Precipitator Sump Equipment Installation

Scope of Work

Rerouted sump discharge piping from the ash ponds to the new on-site water treatment facility. The work included the structural, mechanical, and electrical installation of a new piping system containing three thousand five hundred (3,500) linear feet of pipe and sixty-five thousand (65,000) linear feet of electrical cable. During the completion of the project, an additional five million ($5,000,000) was awarded for time and material-based work, which more than doubled the size of the contract. Although the project scope grew, the project was completed while adhering to the originally agreed-upon schedule.

Project Details
  • Constructed various engineering design changes, owner-requested changes, and punch list-related scopes.
  • Peak workforce of more than ninety (90) craftspeople.
  • Installed twenty thousand (20,000) linear feet of low-voltage cable as part of these efforts.
  • Rerouted sump discharge piping from the ash ponds to the new onsite water treatment facility.
  • Installed a new piping system containing three thousand five hundred (3,500) linear feet of pipe and sixty-five thousand (65,000) linear feet of electrical cable.
  • Assisted the client with start-up and commissioning to ensure a successful turnover.
Lean, Innovative and Unique Project Solutions
This project continued through the COVID-19 pandemic while adhering to the original schedule while adapting to the centers for disease control (CDC), government agencies, the client, and Cianbro's policies and procedures.
No items found.

Our Offices
Corporate Headquarters
P.O. Box 1000
Pittsfield, ME 04967
207-487-3311
info@cianbro.com

Email Us

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.